The Sagrada Família isn't finished: what was completed in 2026 and what's really left
On June 10th, the cross atop the tower of the Church of Jesus Christ was blessed, and many online sources declared the project complete. However, the basilica itself announced today that 70% of the construction is finished, with five construction fronts still active. What has been completed, what remains to be done, and why there is no set completion date. Verified on September 9, 2026.
On June 10, 2026, with Pope Leo XIV present and the temple full, the cross that crowns the tower of Jesus Christ was blessed. The following day, a significant portion of the internet declared the basilica completed. On the basilica's own website, both that day and today, the construction progress section opens with a different figure: a 70% completed.
Both of these things are true simultaneously, and the distance between them is what this article addresses. What will be completed in 2026 is not the Sagrada Familia itself: it is the exterior of just one of its towers, the tallest one, and with it, the final height of the building. What remains to be done is still listed, with names and details, on the official project website.
What will be completed in 2026: a tower, and the exterior work
The piece is the cross of the tower of Jesus Christ, and its technical specifications were published by the basilica's blog on March 2, 2026: 17 meters high by 13.5 meters wide, within a spire 29 meters high, supported by a base of 12 meters. It is made of glazed ceramic and glass, in white, and its geometry repeats the double twist that Gaudí used in the temple's columns. At the base, there is a hexagonal mosaic with a Latin inscription: Tu solus Sanctus, Tu solus Dominus, Tu solus Altissimus.
The same technical sheet reveals a detail that few people mention: the ends of the arms have automated natural ventilation to control the temperature inside, and at night, the cross is illuminated by spotlights placed on the surrounding towers. Furthermore, the design itself wasn't invented in 2026; it was based on a mold of two arms created by Gaudí himself.
With that piece, the temple reached 172.5 meters, its final height, on February 20, 2026. The blessing took place almost four months later, on June 10, exactly one hundred years after the architect's death. And there lies the first misunderstanding of the year: the centennial is of Gaudí's death, not of the completion of the work. The coincidence of dates was intentional. The conclusion that many people drew from it, however, was not.
And what about the "tallest church in the world"? The information is circulating everywhere, but its origin is not the monument itself: the basilica does not claim this in any of its publications. Its current information section contains over six hundred entries, and in the review we conducted from May 2025 onwards, the record does not appear anywhere. The press and encyclopedias attribute it to the basilica. If it is cited, that is the source that should be named.
Something similar happens with Montjuïc. It's often repeated that Gaudí wanted the tower to be located below the mountain so that human creation wouldn's surpass that of God. Then, the discrepancy arises: one meter, half a meter, three meters. The heights published for Montjuïc don't match each other, so we won't find another figure here. The intention is documented, but the exact number is not.
70% of the content is published directly by the basilica itself
The official blog has a section called "Construction Progress." Today, September 9, 2026, it estimates the construction at 70% and lists five ongoing projects: the Chapel of the Assumption, the second sacristy, the Tower of Jesus, the facade of Glory, and sections of the adjacent cloister.
That list needs to be read twice. Three months after the dedication, the Christ the Redeemer statue is still listed as an ongoing project on the monument's own tracking page. This isn't a mistake: what was completed in June was the exterior. The interior is a separate project, and it's still in progress.
Of the other four sections, two are elements that Gaudí had already designed, but which most visitors are unaware are still incomplete. The second sacristy is still used as an entrance and storage area, so it will likely be one of the last sections to be completed. The Chapel of the Assumption faces Provença Street and has been under construction for years. The cloister sections connect the entire complex from the exterior. And the facade of the Glory, which is the main entrance to the temple, doesn't even exist as an entrance yet; it's a project that hasn't even obtained all the necessary permits.
You cannot climb the tower of Jesus Christ, and the entrance with the tower leads to another area
This is the section that generates the most revenue and the one that is least clearly explained. The basilica sells four types of tickets today, priced at €26, €30, €36, and €40, as listed on its own price list. Two of them include access to a tower. Neither of them includes access to the tower of Jesus Christ.
The towers that can be visited are those on the facades depicting the Nativity and the Passion, and you choose one when you purchase a ticket. The tower depicting Jesus Christ is not yet available for visitors and is not for sale. This information is stated on the official website for the centenary celebration, in the frequently asked questions section, with very clear wording.
Once it is officially opened, it will take several months before the tower is accessible to the public. Details regarding the access conditions and schedule will be announced at a later date.
Those "few months" were written before the inauguration. Three years have passed, and the calendar is still not published. Almost everything known about the space comes from the press: a glass elevator that goes up to the heart of the cross, and a capacity of about ten people per turn, according to what Metrópoli Abierta reported in March 2026. It is the most commercially valuable question in the entire sector, and today it still has no answer.
And one uncomfortable thing about the towers that you can climb: the basilica does not publish its rules anywhere. There is no official page with information about the number of steps on the descent, the minimum age, or the operation of the elevator. Four different figures for the number of steps circulate online, so we still cannot provide any specific information. The terms and conditions of purchase, which are published, are detailed in the four types of tickets for the Sagrada Família.
When will the Sagrada Familia be completed? Four conflicting answers
There is no official completion date for the project. There have been various statements made, and they contradict each other. When put together, they reveal a lot more than any single statement on its own.
| Who says that? | When it was said | What's the deadline? | What is it about? |
|---|---|---|---|
| Jordi Faulí, lead architect | June 10, 2026 | "A little over 10 years." | "Most" of the temple, not the end |
| Jordi Faulí, lead architect | June 10, 2026 | "Maybe in 10 years." | Only the four towers of the Glorious Facade |
| Constructora Junta, via El Nacional | September 19, 2024 | By 2033 | The facade of the Glory, without the staircase |
| Constructora Junta, via El Nacional | February 14, 2025 | Approximately 10 years since that date | The Gloria monument, located within the grounds, features no staircase, no overhanging structures, and no more than 100 sculptures |
| The staircase on Mallorca Street | Verified on September 9, 2026 | No date | He doesn't have a license, and the board hasn't ruled out taking the matter to court |
The initial phase, which we are discussing here, is scheduled for June 2026, with the remaining work expected to be completed "a little more than ten years" later, in 2036 or beyond. Faulí didn't specify a precise year; he gave a timeframe and stated "the majority" would be finished, which is not the same as saying it would be completely finished. In the same interview, he listed what would still be outstanding even then: the Portal of Glory, the Chapel of the Assumption, and the second sacristy.
There's a section that summarizes it better than any statement. In January 2026, before the year of the centennial began, Infobae headlined: "2026, the year that couldn't be." It was right, even before it started.
The facade of the Gloria building, the staircase, and a block of apartments
The main entrance still doesn't have all the necessary permits
The Glory façade, located on Mallorca Street, is the main entrance to the temple and the part that Gaudí left the least developed. In March 2025, the basilica announced the start of a new phase: the construction of its four towers, with the goal of completing the eight columns that will support them that same year. In the same announcement, the basilica commissioned decorative proposals from three artists: Miquel Barceló, Cristina Iglesias, and Javier Marín.
The remaining issue is not a constructive one. It's an urban planning problem, and it's better understood from above than from street level: the temple occupies an entire block in the Eixample district, and the missing entrance would have to extend beyond the boundaries of that block.
According to what El Nacional published in February 2025, the license covers the structure of the facade, its four towers, and the eight columns, all within the property boundaries. It does not cover an exterior row of six columns that support cantilevered hyperboloids and extend approximately five meters beyond the property line. It also does not cover the staircase.
The staircase is the critical point. The building's facade would be about four meters above street level, requiring an access portico that would span Mallorca Street. Constructing this would necessitate the expropriation of several properties. How many? This is a question that no one can answer consistently: the figures circulating vary significantly, so this article will not provide any. However, the position of the construction committee is clear. In September 2025, its chairman, Esteve Camps, summarized it in four words: "The staircase will be built," and added that he did not rule out the possibility that a judge would ultimately make the decision.
The two things together give a measure of the situation. The part of the basilica that Gaudí cared about as an entrance, the part that organizes the entire symbolic journey of the temple, which is described on the architecture and symbolism page, is also the only part that depends on an agreement with the residents of a city block. One hundred and forty-four years of work, and the remaining obstacle is a municipal permit.
One hundred and forty-four years, across eight different dates
The first six are closed. The last two are announced deadlines, not official dates.
The origins
1882
Cornerstone
It will be installed on March 19th. The approved design is neo-Gothic, and it is not by Gaudí.
1883
Gaudí takes over
At the age of 31, he took over the direction of the project and completely redesigned it. He worked on it for forty-three years, the last of which were dedicated exclusively to it.
1925
The first tower completed
The tower of Bernabé, on the facade of the Nativity, is now complete. It was the first tower that Gaudí saw finished, and the basilica will hold the opening ceremony of its centenary celebration there in the autumn of 2025.
1926
Gaudi dies
On June 10th, three days after being hit by a tram. The crypt, the apse, and part of the facade depicting the Nativity remained standing in the temple.
The growth
2010
Dedication
Pope Benedict XVI consecrated the temple and granted it the title of minor basilica. It is not the cathedral of Barcelona; that is the Cathedral of Santa Eulàlia, located in the Gothic Quarter.
Today
2026
172.5 meters
On February 20th, the final piece is put in place, and the temple reaches its final height. On June 10th, the centenary of Gaudí's death, Pope Leo XIV blesses the cross.
Announced for 2028
The interior of the tower
This is the year in which the completion of the interior of the Tower of Jesus Christ was announced. However, no official source has confirmed a specific date.
2036 or later
"The majority" of the temple
The timeframe mentioned is based on the deadline given by the lead architect on the day of the blessing. It's not a completion date, as there is no official one.
You visit it just the same, and the building itself is also the artwork
None of the above reasons should deter you from visiting. The Sagrada Família has been fully accessible from the inside for years: the naves are complete, the stained glass windows are in place, and the forest of columns is finished. What remains under construction is mostly located above and outside, and visitors pass through it without even noticing.
There's even a calendar-related argument in favor of going now. This is the last long period in which you can see the temple changing. Those who climbed a tower in 2015 saw a different silhouette than what you see today, and those who climb in 2032 will see another. The complete history of those one hundred and forty-four years is on the basilica's history page, and what has been planned for the anniversary is on the 1926 centennial page.
The questions that always arrive
Is the Sagrada Família construction complete?
No. What was completed in 2026 was the exterior of the Christ the Redeemer tower, the tallest of the eighteen planned. According to the official blog's construction progress update, the project is currently 70% complete, and it lists five ongoing work areas, including the tower itself, as its interior is still under construction.
What exactly ended in June 2026?
The cross that tops the tower of Jesus Christ, and thus the temple's final height: 172.5 meters, reached on February 20th. The blessing ceremony took place on June 10th, on the centenary of Gaudí's death, and was presided over by Pope Leo XIV.
Can you go up to the Christ the Redeemer statue?
Not yet, and there is no date set. The official FAQs for the centennial celebration state that it will take several months after the opening, and that the conditions and schedule for access will be published later. The €36 and €40 tickets provide access to a tower on either the Nativity or the Passion facade, which you choose when you purchase the ticket, not to the tower of Jesus Christ.
When will the Sagrada Família be completed?
There is no official date. On the day of the blessing, the chief architect stated that the majority of the temple could be completed in a little over ten years, which would be in 2036 or later. In 2024, the construction committee projected completion of the facade of Glory (without the staircase) by 2033. The staircase does not yet have either a permit or a projected completion date.
Is it the tallest church in the world?
With a height of 172.5 meters, it surpasses any other church, a fact that is reported by the press and encyclopedias. It's important to note that the basilica itself does not claim this record in any of its official publications. If this figure is cited, the source is not the monument itself.
What still needs to be built?
According to the official project list: the Chapel of the Assumption, the second sacristy, the interior of the Christ the Redeemer tower, the Façade of Glory, and sections of the cloister. The sacristy will be one of the last to be completed, as it is currently used as an entrance and storage area for materials. Almost everything is missing from the Façade of Glory, including the staircase that would cross Mallorca Street.
Is it worth visiting while it's under construction?
The interior has been completed for years: the nave, columns, stained glass windows, and museum are all fully accessible. What remains unfinished is located above and outside. Furthermore, there's a temporal element to consider, as the structure changes every few years: a visit in 2032 will not be the same as a visit today.
People who climb a tower
The towers that can be climbed today are the Nativity Tower and the Passion Tower. These are the experiences offered in the catalog that include access to these towers.
Barcelona Pass with access to the Sagrada Familia towers
This pass includes access to the temple towers, as well as Park Güell, and offers several city tour options, all with a single purchase.
Guided tour of the Sagrada Família in English, including the museum and Gaudí's workshops
Before entering, you can admire the two facades, the nave, and the altar. The museum at the end showcases Gaudí's sketches and models. Wheelchair access is not available.
Guided tour of the Sagrada Familia with direct entry
A one-and-a-half-hour guided tour of the three facades and the forest of columns, including entrance fees, followed by free time to explore the museum and the crypt.
Guided tour: Sagrada Família and Park Güell in a single itinerary
Both sites can be visited in a single tour with just one guide, who seamlessly connects the explanation of the temple with that of the park, rather than repeating the information.
Ratings collected by Tiqets, Viator, Tripadvisor and Civitatis
Data verified on. The project status, fees, and schedule were reviewed on September 9, 2026, on sagradafamilia.org, its blog, and sagradafamilia2026.org. The statements mentioned are those published on the websites listed, with their respective dates. Sobre este sitio